Introduction: CDU capacity steps, redundancy, and interface boundaries in a colocation hall must serve phase one and phase four alike.
A colocation hall rarely fills under one contract. In a multi-tenant colocation, the planning manager commits zone loads long before tenants sign leases. Phase one might be a single 600 kW hall with two anchor tenants; phase two adds a GPU row; phase three splits a floor into metered blocks with different density profiles. Each decision locks in a pipe size, a pump configuration and a temperature basis that later phases inherit. Mistakes rarely appear as a dramatic failure at first. They surface as adapter spools, re-piped manifolds, mismatched valve sets and control logic rewritten while tenants are already running. The practical response is to choose capacity steps you can repeat, decide where pump redundancy is worth the extra hardware, and keep every interface boundary compatible as new zones come online.
How Should Colocation Operators Divide Phased Loads Across CDU Capacity Steps?
Start with the zone load, not the rack count. A phased colocation plan is easiest to hold together when each zone maps to one CDU or a small group of identical CDUs, because metering, isolation and maintenance stay local to a tenant block. The Zejiu GLU series covers five capacity steps at 300 kW, 600 kW, 900 kW, 1200 kW and 1800 kW. Those steps divide cleanly: two 300 kW units match one 600 kW unit, two 600 kW units match one 1200 kW unit, and two 900 kW units match one 1800 kW unit. That doubling pattern makes a standard step reusable. An operator can build phase one around 600 kW zones and later add 1200 kW zones with the same control philosophy. Lock the flow values early, because they set pipe size and pump duty. Record heat load in kW and secondary flow in m³/h on the same zone schedule. The 300 kW step moves 25.7 m³/h on the secondary side, 600 kW moves 51.4 m³/h, 900 kW moves 77.1 m³/h, 1200 kW moves 102.9 m³/h and 1800 kW moves 154.3 m³/h. Where the project combines CDU supply with secondary-loop integration, a liquid cooling system integrator CDU supplier can use the same schedule to check each later phase against one baseline. Tenant granularity is the third input. A 1800 kW unit serving an entire hall looks efficient on paper, but it ties every tenant in that hall to one maintenance boundary and one metering point. Smaller repeated zones cost slightly more floor space and connection hardware, yet they let a tenant leave, expand or shift density without touching neighbouring blocks. A mixed schedule often works best: 600 kW zones for early stages and lower-density general compute, stepping up to 900 kW or 1200 kW zones where GPU tenants have firm density commitments. The capacity step becomes both a commercial unit and an engineering rating.
Where Should Dual-Pump Redundancy Enter a Phased CDU Plan?
Redundancy is a lease decision before it is a hardware decision, and the capacity step makes that decision concrete. The 300 kW and 600 kW units use single pumps; the 900 kW, 1200 kW and 1800 kW units use dual pumps. That boundary is a natural dividing line in many phased plans, because the size at which a zone starts carrying committed high-value tenants is often the same size at which tenants ask what happens during pump maintenance.
1. Place Dual-Pump Units at 900 kW and Above for Committed Critical Zones
From 900 kW upward, each unit carries two pumps, with single-pump flow of 39 m³/h at 900 kW, 51 m³/h at 1200 kW and 77 m³/h at 1800 kW, and head of 35 m, 36 m and 38 m respectively. That provides pump-level redundancy inside the zone, which aligns with general reliability practice for continuous-duty facilities. Use those units where the tenant agreement names maintenance windows and uptime expectations, such as GPU halls on committed contracts or zones serving more than one paying tenant. Dual-pump redundancy supports pump maintenance; it does not mean zero downtime. Changeover still depends on isolation valves, control sequencing and an agreed maintenance window, so the redundancy scope should match the reliability design the tenant signed up for.
2. Keep Single-Pump Units for Early-Stage and Lower-Density Zones
Early phases and lower-density general compute zones rarely justify the extra pump, and the 300 kW and 600 kW steps fit that job directly. The 300 kW unit runs a single pump at 26 m³/h and 30 m of head with a DN50 manifold, while the 600 kW unit runs a single pump at 51 m³/h and 30 m of head with a DN65 manifold. These are sensible first-phase choices: they prove the loop, serve tenants with modest density, and keep capital outlay proportional to signed load. Keep the room layout, service clearance and connection boundary identical to the dual-pump template. A later phase can then install a 900 kW or 1200 kW dual-pump unit in the adjacent slot without re-routing headers or rethinking maintenance access.
How Can DN50 and DN65 Interfaces and 5°C Approach Stay Compatible Across Phases?
The interface plan has one clear step change to manage. DN50 is used only on the 300 kW unit; every other step from 600 kW to 1800 kW uses DN65. A first phase built on 300 kW zones therefore sits on a smaller header size than everything that follows. Plan that boundary deliberately rather than discovering it during phase two: terminate the DN50 zone at a transition assembly sized for the later flow, and keep the isolation valves and connection type consistent on both sides so the changeover is a planned operation rather than a field modification. Friction loss rises steeply as velocity climbs, so size the transition for the highest eventual flow that will pass through it. Temperature compatibility is the easier half, and it is the reason a phased plan can stay calm. All five steps share the same 5°C approach temperature, the same primary water range of 5-40°C and the same secondary water range of 10-45°C. Phase four can use the same primary loop set point as phase one, and the control logic can stay on the same temperature basis as new zones are added. Each phase still needs its own zone load, actual water temperatures at the connection point, measured pressure drop across that zone's loop and interface drawing showing where the CDU boundary ends. A data center liquid cooling CDU supplier can review a phased project properly only with those four inputs and a stated redundancy target for each zone. Those inputs turn the plan into a CDU data center liquid cooling solution with repeatable capacity steps, pump scope and interface boundaries.
Conclusion
Phased colocation builds reward operators who choose repeatable capacity steps, place pump redundancy where the lease demands it, and treat the DN50-to-DN65 boundary as a planned transition. The 300 kW to 1800 kW range covers both the small proving phase and the dense GPU hall, and the shared 5°C approach with common water temperature ranges keeps every phase on one thermal basis. Send the zone load schedule, water temperatures, pressure drops and interface drawings for review, and our engineering team can confirm the capacity step, pump configuration and manifold size for each phase before a quote is issued.
FAQ
Q: How should a colocation operator plan CDU capacity for a phased GPU hall?
A: Map each zone to a load figure first, then match it to one of the five steps at 300, 600, 900, 1200 or 1800 kW so later zones repeat a size you already support. Keep secondary flow per zone on the same schedule—25.7, 51.4, 77.1, 102.9 and 154.3 m³/h—and reserve the 900 kW and 1200 kW steps for GPU zones with committed density.
Q: At what capacity step should dual-pump redundancy enter a phased CDU plan?
A: The natural entry point is 900 kW, because the 900 kW, 1200 kW and 1800 kW units carry dual pumps while the 300 kW and 600 kW units use single pumps. Bring dual-pump units in as soon as a zone serves committed high-value tenants with named maintenance windows. Leave early or lower-density zones on single-pump units until their lease terms justify the change.
Q: How can later phases keep DN50 and DN65 interfaces compatible with earlier phases?
A: DN50 applies to the 300 kW step and DN65 to the 600 kW to 1800 kW steps. Build the small step with a transition assembly and matching isolation valves sized for the future flow. Keep the connection type and valve set consistent on both sides, and confirm the pressure drop at each zone boundary as phases are added.
Sources / References
IEEE 3006.7 - Recommended Practice for Determining the Reliability of 7x24 Continuous Power Systems
Hazen-Williams Water Flow Formula: Head Loss, Data, Charts & Calculator